The construction industries are relatively conservative type of business that takes a long
time to adjust for new methods and embrace new ideas. It dose not matter if the new
method seems to be an improved method as long as it is new and untried. Construction
companies are reluctant to change form a longtime working method to a relatively
unknown method.
The purpose with our report is to perform an evaluation of BeWi construction method.
Our goal are to present the generally opinion about BeWi from the contractors that has
been in contact/worked with the method. We also want to know from the contractor’s
point of view if BeWi and the method measure up to the standards that are presented by
BeWi and if they believe that improvements need to be done.
Our progress up to the final report has consisted of three parts
[1]Field studies
[2]Interviews
[3]Literary studies
We started out with field studies where we took notes and observed all the included
working phases on the construction site when using the BeWi method. Also during our
field studies we ourselves tried working with the method for a more close experience of
the work environment.
As conclusion we can say that BeWi construction method undeniable are an easy- going
and working method that improves the work environment for the construction workers
and also has the potential that can lead to better results.
The system is based on a new kind of method which can lead to complications during the
first times working with it, but the commissioning period relatively short. From an
economical point of view the material costs are higher than a regular wooden foundation
but we believe that you can compensate this in the long run with the low energy costs that