Examensarbete, grundnivå
Småhusproduktion
Utvecklingsmöjligheter hos JM AB
Sammanfattning
The Swedish building contractor JM
Region Öst would like to to investigate
the possibilities of developing and
streamlining the production of singlefamily
houses. JM are producing singlefamily
houses with prefabricated frames
at a rate of about two houses per week.
During construction, the different tasks
are performed by JM’s own production
staff but also by various
subcontractors.
When examining the schedules of recently
produced projects, it appears that all
the houses are more or less completed
eight weeks before the customer moves in
to the house. During those eight weeks
several operations are conducted such as
inspections, installation of appliances
and cleaning procedures. The inspection
period constitutes between 25 and 35% of
the complete construction period.
By conducting interviews, it has been
discovered that this final phase is an
essential security buffer for delays and
errors that often occur. Reducing the
time needed for inspection requires that
all activities are properly conducted
with the right quality from start.
After analyzing the results of the
interviews and the comparison of project
schedules, the following conclusions
have been made:
? The time required for
inspections at the end of each project
can be reduced if at the same time
quality inspections and management of
subcontractors are improved during the
whole of the construction period.
? The construction rate is
difficult to increase as it is depending
on the supply capacity from the house
supplier.
? The experience feedback at JM
can be improved, mainly through feedback
to the production staff at the beginning
of new projects